The crews working under Agoura Road between Lindero Canyon Road and Lakeview Canyon Road are laying pipe that will carry the first drinking water this area has ever produced for itself. Right now, all of the water that reaches a Westlake Village tap comes from Northern California. This dig is one of the early steps toward changing that.

The work belongs to the Pure Water Project Las Virgenes-Triunfo, a joint effort of the Las Virgenes Municipal Water District and the Triunfo Water and Sanitation District. The two agencies run it through a Joint Powers Authority, usually shortened to the JPA. Valley News Group reported on October 9 that the JPA had started "urgent pipeline repair and installation work" on this stretch, and that the work is needed to connect the parts of the project.

What the Corridor Looks Like Through Winter

The JPA posts a construction update every week. Its update for the week of October 26 put crews near Greengate Court, working west as they go. The work includes asphalt removal, excavation, pipeline installation and repair, underground equipment and temporary road patching. Drivers should expect temporary lane closures, traffic shifts, turn restrictions, parking restrictions and flaggers as the work moves through each phase. The JPA says access to nearby homes and businesses will stay open "whenever possible."

The two published sources give different work hours. The JPA's weekly page lists Monday through Friday, about 7 a.m. to 4 p.m., and says hours may change by activity and location. The Valley News Group story says the work will happen during both daytime and nighttime hours, so people nearby may see crews in the evening and overnight. If you live or work near the corridor, plan for both.

Both sources estimate four to six months of work. The work started in early October, so that estimate ends somewhere between early February and early April 2027. The JPA adds that weather and field conditions can change the schedule.

Oliver Slosser, Engineering Program Manager at Las Virgenes Municipal Water District, told Valley News Group that "construction of this scale affects the daily routines of residents, commuters and businesses."

The Westlake Village stretch is only one part of the work. Next door in Agoura Hills, the JPA's late-October update listed utility work and lane restriping on parts of eastbound Agoura Road, tentatively planned for early November, with fewer lanes and possible delays. If you drive east toward Agoura Hills, you may pass through two work zones in the same trip. The project helpline is (818) 245-4440, and you can sign up for Westlake Village email updates on the JPA's construction page.

Today, Every Glass of Water Comes From the Sierra

Las Virgenes Municipal Water District serves Westlake Village. According to the district's water supply conditions page, all of its drinking water comes from the State Water Project through the Metropolitan Water District of Southern California, and the California Aqueduct carries it down from the Northern Sierra. That means snowpack and reservoir levels hundreds of miles away decide how much water the district gets. During the worst of the last drought, the district says its customers faced a mandatory 73% cut in water use.

That 73% cut is the problem the Agoura Road pipe is meant to address. The district calls Pure Water its "first local source of drinking water." Speaking at the April groundbreaking, as reported by the Thousand Oaks Acorn, LVMWD board vice president Jay Lewitt explained the stakes:

"Up until now, we've been 100% (dependent) on imported water through the State Water Project. The advanced water treatment facility will make us less dependent on imported water."

The Acorn reported that he put the reduction at about 30%. The JPA uses a similar figure and says the finished project could supply up to 30% of the region's drinking water.

The Route From Sewer to Faucet, Stop by Stop

The water will make five stops before it reaches a Westlake Village kitchen. Most of them are close to home.

  1. Tapia Water Reclamation Facility on Malibu Canyon Road. Wastewater from homes and businesses in the Malibu Creek watershed is already treated here. Right now that treated water is used for irrigation in summer, and the extra is released into Malibu Creek in winter.
  2. The Advanced Water Purification Facility at 30800 Agoura Road, Agoura Hills. The Acorn described the site as LVMWD property south of Agoura Road, close to the Westlake Village border. The plant will purify the water three ways: membrane filtration, reverse osmosis, and ultraviolet light with advanced oxidation.
  3. New pipelines. The plan calls for about 20 miles of pipe and supporting infrastructure. The pipe going in under Agoura Road is part of this network.
  4. Las Virgenes Reservoir. The purified water will be mixed with imported water here. Because the reservoir sits between the plant and the tap, the JPA calls the method "indirect potable reuse," with the reservoir serving as a natural buffer.
  5. Westlake Filtration Plant. The water gets one last round of treatment here before it goes into the delivery system.

The first stop is in the Malibu Canyon area, and the next four are on the Agoura Road plant site, under area streets or at the reservoir and filtration plant. Today, Westlake Village's water travels hundreds of miles from Northern California. When Pure Water is running, part of the supply will come from wastewater treated a few miles away at Tapia, purified on Agoura Road and stored in a nearby reservoir.

A Calendar That Runs to 2030

The Agoura Road work is measured in months, while the full project runs on the JPA's multiyear schedule:

Phase JPA timeframe
Ceremonial groundbreaking in Agoura Hills April 10, 2026
Construction of plant and pipelines Spring 2026 through Fall 2028
Pipeline and facility testing Through Winter 2029/2030
Operations expected to begin Spring 2030

The plant is designed to take in 7.5 million gallons per day and can eventually be expanded to 18 million. It's expected to produce about 2,100 acre-feet per year at first, with a goal of 5,000 acre-feet per year by 2040. Walsh Construction, Jacobs Engineering, and Brown and Caldwell are building it with the JPA. At the plant site, the JPA's update lists excavation, concrete walls for an equalization tank, foundations for the treatment building, and underground piping. Its plant construction page adds earthwork, backfilling and work on a retaining wall. Building the plant also means removing protected native oak trees, which triggers replacement requirements under state, county and Agoura Hills rules.

The Price Tag, and How It's Being Paid For

The JPA puts the whole project at about $466 million, with roughly $303 million of that set aside for design and construction. That explains why the Acorn's April headline mentioned a "$300-million" plant. Both figures are correct; they measure different things.

On September 18, 2026, LVMWD announced more than $335 million in state and federal financing. That includes $84 million in loans and grants from the State Water Resources Control Board, of which $15 million is grant money, plus a $251 million federal WIFIA loan from the U.S. Environmental Protection Agency. The district projects that the state package will save about $10 a month on customer bills compared with market-rate financing. A JPA chart on the project's cost and funding shows an expected impact of $13 a month on ratepayers.

What the Project Ends, and What It Sends Through Thousand Oaks

The project also changes what happens to Malibu Creek. Each winter, when less recycled water is needed for irrigation, Tapia releases the extra into the creek. The JPA says tighter nutrient limits have made those releases costly and hard to sustain. Pure Water sends that water to the new plant instead. The JPA says the other option would have been more than $200 million in upgrades at Tapia just to stay in compliance.

Reverse osmosis leaves behind salty brine, and that brine needs somewhere to go. The Acorn reported that a brine line will run from Westlake Village through Thousand Oaks to Newbury Park. There it will join an existing pipeline owned by Calleguas Municipal Water District that carries the brine to the ocean at Port Hueneme. The Acorn also reported that Calleguas and Las Virgenes are now connected, so they can share water during a drought. Thousand Oaks lists the pipe's route along Agoura Road, Conejo School Road, Hillcrest Drive, Ventu Park Road, Rancho Conejo Boulevard and Hill Canyon Road to Santa Rosa Road, with the last section scheduled to finish by March 2028. The JPA's late-October update showed crews already on East and West Hillcrest Drive. If you drive between Westlake Village and Newbury Park, you'll likely run into this project in more than one spot.

You Can Taste the Water Now

The full plant won't run until 2030, but a small version is open now. Las Virgenes built the Pure Water Demonstration Facility in Calabasas to test the process and show the public how it works. KCLU reported that visitors can see the small plant running and taste the water. The JPA says the facility has hosted hundreds of public tours, and you can book one at ourpureH2O.com/demonstration-facility. It's a good thing to do on a weekend with kids, or with guests who ask why Agoura Road is down to one lane.

We follow projects like this one because they shape everyday life in Westlake Village long after the barricades come down. If you'd like to talk about how changes along Agoura Road and around town fit into your plans for your home, the team at McQueen & Associates is always glad to talk. You can start with a free estimate of what your home is worth.

Your Journey, Our Expertise — Let’s Get Started —

Your real estate journey deserves a team that truly understands your needs. With years of local expertise, McQueen & Associates is here to offer you the tools, insights, and dedication you need to succeed.

Follow Us on Instagram